Sustainable Energy Operations
Mansuriya Gas Field
Location
History
Key Reservoir Details
The estimated OGIP is 4-4.5 TCF.
Strategic Partnership
The approved investment budget for the initial 3 year period is $992mn.
Development Plans
Petro Iraq’s development plan is focused on optimizing the Mansuriya Gas Field to achieve sustainable production growth. To learn more about the key milestones and strategies behind each phase, explore the details of Phase I and Phase II below.
Phase I: Initial Development and Optimization
Production Target
Achieve 100-130 MMSCFPD of gas and 11 KBCPD of condensate using 3 existing wells and new wells.
Well Utilization
Utilize 3 of the 4 existing wells while drilling additional wells for further reservoir data.
Appraisal and Delineation Wells
Drill new wells to gather critical reservoir data for better field assessment.
Optimization for Phase II
Use Phase I data to refine and optimize development for Phase II production.
Phase II: Expansion and Peak Production
Peak Production Target
Reach 350 MMSCFPD of gas within 5 years, with significant condensate production.
Well Drilling
Drill additional wells to enhance production capacity and reservoir data.
Central Processing Expansion
Expand the central processing facilities to support increased production and processing.
Sales Gas and Condensate
Achieve 300 MMSCFPD of sales gas and over 30 KBCPD of sales condensate.